And even better...
There are serious problems and issues with the contractual documents provided by UKPC in their amended Particulars of Claim. These relate to their alleged authority to operate and issue PCNs at Parkhouse Court as of 19 November 2017, the date of the alleged contravention:
1. No Document Dated 2017 (or Earlier)• There is no evidence of a contract or landowner agreement in place at the time of the alleged contravention on 19 November 2017.
• The only document shown in the PoC is a letter from Ian Gibbs Chartered Surveyors dated 16 May 2019 — that is 18 months after the incident.
Therefore, there is no proof that UKPC had the authority to issue PCNs at that site on the material date.
2. Post-Event Letter, Not a Formal ContractThe 2019 letter (Appendix A) is not a formal contract, does not name the landowner, and merely states in general terms that UKPC is “authorised by Hatfield District Estate Management Company Ltd c/o Ian Gibbs.”
It provides no detail about:
• When the authorisation began;
• The contractual terms;
• The duration of the agreement;
• Who signed it on behalf of the landowner;
• Any reference to 2017 or retroactive coverage.
3. Letter is Unfit to Prove Contractual StandingFor a private parking company to pursue a PCN in court, they must show a valid written agreement in place on the date of the alleged contravention.
This 2019 letter:
• Appears to have been created for litigation purposes (likely on request by UKPC);
• Does not confirm the agreement was retrospective;
• Contains no reference to contractual rights in 2017.
4. Fails to Comply with the Code of PracticeUnder the BPA Code of Practice (in force in 2017), Section 7.1 required:
“You must have the written authorisation of the landowner or their appointed agent before you can carry out any parking control and enforcement.”
The authorisation must be available on request and must:
• Include the date it commenced;
• Be signed;
• Clearly define the operator’s powers.
The letter from Ian Gibbs does none of this.
5. Appendix A is MisleadingThe PoC describes Appendix A as “
the letter from the landowner’s agent confirming our authority to operate at the site,” but:
• It is not signed by the landowner;
• It does not contain contract terms;
• It is dated May 2019, which undermines any claim of prior authority.
6. No Site Plan, Schedule, or Signature PageA proper contract or licence agreement should contain:
• The full names of both parties;
• A clear site plan showing the land covered;
• A schedule of commencement/expiry dates;
• Signatures from both parties;
• Specific reference to PCN enforcement rights.
None of these have been provided.
Conclusion: Major Evidential GapsThe documents provided:
• Do not prove that UKPC had any valid contract or authority at the location in 2017;
• Are legally insufficient to establish contractual standing to pursue the PCN;
• Should not be accepted by the court as evidence of authority.
If this does have to be defended again, you will be asking for further costs sue to clear unreasonable behaviour by the claimant and their useless solicitors.